Total estimated cost. CZK 12-12 million (2018)

Total invested so far: 1 255 800 CZK

    Phase I (January to May 2016)

    The aim of Phase I of the project was to create the first architectural study for the accessibility of the church’s leaning tower by architect Martin Rajnis and to present it to the key players, i.e. The first key elements of the project were the design of the building and its key stakeholders – the Archdeaconry of Ústí nad Labem, the National Heritage Institute and the Regional Administration of the Fire Brigade.

    Total cost of Phase I: CZK 234 740

    • 3D orientation of the church
    • architectural study

    II. Phase II (June 2016 to July 2018)

    Objective II. phase of the project was to prepare a fire safety solution, modify the architectural study and renegotiate it.

    Total cost II. Phase II: 159 560 CZK

    • preparation of an engineering geological report
    • preparation of a mycological report
    • engineering activities
    • legal services
    • elaboration of a fire safety solution

    III. Phase III (July 2018 to August 2019)

    Objective III. phase of the project was to complete the architectural study.

    Total cost III. Phase III: 136 881 CZK

    • modifications of the architectural study
    • modifications to the fire safety solution

    IV. Phase IV (September 2019 to December 2021)

    Goal IV. phase of the project was to obtain binding opinions from the authorities concerned.

    Total cost IV. Phase IV: CZK 724,619

      • preparation of project documentation
      • engineering activities
      • Budget

      At 65 metres high, the tower is deflected by 2.09 metres

      okno-v1

      The 4th steepest tower in Europe